Annexes to COM(2020)82 - Implementation of the work under the nuclear decommissioning assistance programme to Bulgaria, Slovakia and Lithuania in 2019 and previous years

Please note

This page contains a limited version of this dossier in the EU Monitor.

agreement on the 2021-2027 MFF.

Table 2:    Payments to end beneficiaries, 30 June 2019    
(€ million)

National resourcesEUTotal
Kozloduy296 (40%)440 (60%)736
Bohunice208 (39%)322 (61%)530
Ignalina175 (15%)1006 (85%)1 181

Source: Monitoring reports, EBRD, CPMA.

4. Progress and performance

The Commission measures progress and performance against the objectives set out in the Council Regulations establishing the programmes. Detailed targets and schedules in the implementation procedures and the EVM system complement the monitoring.

To date, progress against the objectives is generally satisfactory and the cost of the work has been as planned. The programmes’ critical path is monitored with the utmost attention and, when risks are identified, mitigating actions are proposed so that at this point in time the end-dates are still valid. After the mid-term evaluation, the time profile of the activities was revised to re-calibrate the tracking of progress and performance.

4.1.Bulgaria – Kozloduy programme

Units 1‑4 at the Kozloduy plant are VVER 6 440/230 reactors: units 1 and 2 were shut down in 2002 and units 3 and 4 in 2006.

Under the administrative supervision of the Ministry of Energy, the State Enterprise for Radioactive Waste (SERAW) is the operator in charge of the decommissioning of Kozloduy units 1-4 and the construction and operation of the national disposal facility for radioactive waste. Its mission is the safe management of radioactive waste on Bulgarian territory.

The Kozloduy programme made significant progress on dismantling in the auxiliary buildings, e.g. completing the dismantling of equipment in the turbine hall in August 2019, a year earlier than scheduled ( Figure 1 ).

Figure 1:    Before and after dismantling of equipment in the turbine hall    
photo SERAW


The plasma melting facility, a first-of-its-kind facility for the high‑performance volume reduction of radioactive waste, started operations in November 2018 (target: March 2018) and continued with the support of the system provider until the end of 2019. It is now in industrial operation and the technical and financial evaluation of the first operational campaign will be finalised in 2020.

The similar design of the Bohunice and Kozloduy reactors provides an excellent opportunity to share experiences, methods and tools. This knowledge‑sharing reduces risks and cost. For example, in 2019 the feasibility of decontaminating the primary circuits at Kozloduy was confirmed on the basis of experience from Bohunice. The transportation of decontamination equipment used at Bohunice to Kozloduy was then prepared with a view to decontaminating the primary circuits in 2020 (target end date: October 2022).

Permits for the construction of the near-surface repository for low-level waste, the national disposal facility, have been repeatedly challenged in recent years. In 2019, the five members of the Supreme Administrative Court took a final decision confirming the Environmental Impact Assessment decision validity.

The construction works do not imply any radiation or nuclear safety risk, and proceeded as planned ( Figure 2 ). However on 16th December 2019 a fatal accident occurred on the building site. Building activities are suspended until the causes of the accident are fully analysed and all measures are implemented to restart the works under the best Health and Safety conditions.

Figure 2:    Construction of national disposal facility
photo SERAW


In accordance with the updated performance baseline, the programme completion date remains the end of 2030. Figure 3  shows the amount of work carried out (earned value) against the plan (baseline). In 2018, the budget at completion (including contingencies) was revised to €1 358 million. This represents an increase of 23% on the 2014 estimate and Bulgaria has increased its contribution accordingly.

Figure 3:    Kozloduy – progress and performance


4.2.Slovakia – Bohunice programme

The Bohunice V1 plant consists of two VVER 440/230 reactors. Unit 1 was shut down in 2006 and unit 2 in 2008.

Under the administrative supervision of the Ministry of Economy, Jadrová a vyraďovacia spoločnosť (JAVYS) is the operator in charge of decommissioning Bohunice V1. Its mission is the safe decommissioning of the nuclear facilities, spent nuclear fuel and radioactive waste management on Slovakian territory.

The Bohunice decommissioning programme is the most advanced of the three programmes assisted by the EU and will probably see the first complete decommissioning of a VVER‑type reactor.

The programme made substantial progress in 2019. After completion of the dismantling of the turbine hall equipment and the auxiliary buildings, including the demolition of the four cooling towers ( Figure 4 ), the dismantling of the large components in the reactor building started in earnest.

Figure 4:    Before and after dismantling equipment in turbine hall    
Before and after demolition of cooling towers    
photo JAVYS


By July 2019, all 12 steam generators, each made up of 145 tonnes of steel, had been removed from the reactor building and transported to the former turbine hall ( Figure 5 ), where construction of the dry‑cutting workshop was finalised and the cutting equipment for breaking up the generators was installed. In the second half of 2019 (target: second half 2019), the pressurisers were cut up and the construction started of two wet‑cutting workshops in which the reactor internals will be segmented under water.

Figure 5:    Workshop and storage of steam generators in former turbine hall
photo JAVYS


In 2018, 97.5% of the waste handled at Bohunice was recyclable, 1.7% was non-recyclable and 0.8% was radioactive. In 2019, disposal capacity for low‑level waste, representing over 90% of total radioactive waste by volume, was extended by around 30% at the Mochovce repository.

In accordance with the updated performance baseline, the completion date for the programme remains the end of 2025. Figure 6 shows the amount of work carried out (earned value) against the plan (baseline). The budget at completion (including contingencies) was updated in 2018 to €1 238 million, about 1% less than the 2014 estimate. The new estimate is supported by a state-of-the-art plan for risks and contingencies, which provides a high level of confidence.

Figure 6:    Bohunice – progress and performance


4.3.Lithuania – Ignalina programme

The Ignalina plant consists of two RBMK 7 1500 reactors. Unit 1 was shut down in 2004 and unit 2 in 2009.

Under the administrative supervision of the Ministry of Energy, the Ignalina Nuclear Power Plant (INPP) state enterprise is the operator in charge of the facilities under decommissioning and, since 2019, the waste disposal facilities.

The removal of spent‑fuel assemblies from the reactor buildings (units 1 and 2) resumed in September 2016. Both reactors are now completely defueled. The remaining contents of the spent‑fuel pools are being transferred to storage casks and finally to the interim spent‑fuel storage facility. By the end of 2019, over 75% (target: 69%) of spent‑fuel assemblies were safely stored in this new dedicated facility. This operation is scheduled to continue until July 2022.

Meanwhile, INPP has started preparations for the handling of heavily damaged fuel elements and the cleaning‑up, emptying and decontamination of the spent‑fuel pools.

Figure 7:    Casks for spent‑fuel assemblies stored in the interim storage facility
photo INPP


Before (09/2016)


After (09/2019)


With 50 000 tons (target: 40 658 tons) of material dismantled from the turbine hall, the removal and decontamination of equipment is now coming to an end. The building is being used as temporary storage for material undergoing clearance before regulatory control can be lifted and for low‑level radioactive waste before it can be transferred to a final disposal facility.

The dismantling of the Ignalina reactors is a first‑of‑a‑kind challenge: never before has a large power reactor with a graphite core been dismantled. In a first phase (2020 to 2027), INPP will remove all equipment around and on top of the reactor shaft. The subsequent removal of the graphite from the shaft is being prepared with an optioneering 8 study and detailed design of the preferred solution and a facility for the temporary storage of irradiated graphite waste.

Construction of the landfill facility for very low-level waste has been completed and the first loading campaign is scheduled for the second half of 2020. The launch of the procurement procedure for the construction of the near‑surface repository for low‑level waste was scheduled for January 2020 but is delayed by designer approval of technical revisions to comply with public procurement requirements. With those two facilities, INPP will have all the tools it needs for the management, storage and disposal of the radioactive waste under the decommissioning plan.

Figure 8:    New radioactive waste management, storage and disposal facilities


In accordance with the updated performance baseline, the programme completion date remains 2038. Figure 9 shows the amount of work carried out (earned value) against the plan (baseline). The budget at completion (including contingencies) is unchanged, at €3 377 million.

Figure 9:    Ignalina – progress and performance


4.4.Energy sector projects

Until 2013, the assistance programmes allocated funds to energy‑sector projects in line with the respective Member States’ accession treaties and national energy policies. The impact assessment prepared in advance of the current (2014-2020) programmes concluded that those measures would achieve their objectives with the existing funding and should then be discontinued. Therefore, the current programme is limited to implementation of the decommissioning plans, so that it is the focus of the resources and governance structures.

In 2019, the Commission finalised an ex post evaluation of the energy‑sector projects financed in 2007-2013. Over €947 million had been committed in support of 58 projects seeking to achieve:

·environmental upgrading (including energy efficiency);

·modernisation of conventional energy production;

·restructuring and modernisation of electricity transmission and distribution;

·enhanced security of supply; and

·enhanced use of renewable energy sources (Bulgaria only).

The EU co-financing rate averaged 50.4%, with variations depending on the relationship between the project and the early closure of the nuclear power plants, the type of project and the public or private status of the grant holder. Bulgaria accounted for the highest proportion of the committed budget (€401 million) and the highest number of projects (38). Lithuania and Slovakia had fewer projects, but higher average allocation per project (Lithuania: €364 million for 15 projects; Slovakia: €182 million for 5 projects).

Energy projects in Bulgaria targeted the whole value chain, with a stronger emphasis on downstream components (networks and consumption). In Lithuania, the focus was mainly upstream (on production), in particular with the upgrading and modernisation of the country’s largest conventional power plant to replace capacity and partly to comply with the European environmental requirements related to power plant emissions. In Slovakia, the biggest share of resources was devoted to networks, in particular for transmission, in order to improve security of supply.

Figure 10:    Number of energy projects supported according to position in value chain, by country


Overall, 40 energy‑sector projects had been completed by the end of 2019, accounting for 75% of the allocated funds. The last 18 projects are due to be finalised in 2020.

The study concluded that action under the programme was both instrumental and timely in the three countries, as no other programmes could match the scope and number of projects covered. The programme gave effective support to mitigation measures along the energy value chain, according to national needs. It contributed to the building and modernisation of energy networks, facilitating connections and diversifying the energy mix. On the consumption side, it supported the refurbishment of hundreds of public and private buildings and thousands of households, the modernisation of district heating networks, greater energy efficiency in industry and better street lighting in 35 cities.

In the long term, the programme will have helped to:

üimprove security of supply following the loss of nuclear capacities;

üensure reliable electricity distribution;

üfoster integration into the European energy market;

üenhance energy diversification; and

üimprove energy intensity.

It had other, indirect effects, such as enhancing the reliability of power supply, mitigating energy price increases, reducing energy intensity and making local businesses more competitive. It also helped to develop capacities in the three countries, attracting investment, including from private sources.

5. Knowledge‑sharing

More and more knowledge‑sharing is taking place. In March 2019, a fourth trilateral knowledge‑sharing seminar was held in Bohunice. It was attended by the decommissioning operators (JAVYS, SERAW and INPP) and representatives of the Joint Research Centre and the International Atomic Energy Agency.

As the NDAP progress, knowledge‑sharing and synergies are becoming more concrete, resulting in time and cost savings in decommissioning projects. In 2019, the major areas in which knowledge is being shared are the decontamination of primary circuits and the incineration of radioactive waste, via more conventional equipment or the state-of-the-art plasma melting facility (see section 4.1).

In its proposals for new Regulations, the Commission has introduced a requirement that experience and lessons learnt from the programmes be shared across the EU.

6. Conclusions

In line with expectations, Bulgaria, Lithuania and Slovakia continued to make effective progress in decommissioning their nuclear power plants in 2019. Indications to date are that greatly improved safety levels will be achieved at the sites as a result of EU funding under the 2014-2020 MFF.

The governance system has been updated and has proven able over time to cope with challenges and setbacks arising from the complexity of the programmes. Knowledge‑sharing among the beneficiaries has had a positive impact on the programmes and contributed to the latest successes. The Commission has built on that to develop concrete synergies, e.g. in 2020, the decontamination of the primary circuits at Kozloduy will be supported by know-how developed by JAVYS and use equipment acquired under the Bohunice programme.

No additional funding is needed to achieve the objectives set out in the current Council Regulations. Completion of the decommissioning programmes to their planned end‑state will require additional funding in 2021-2027, for which the Commission has proposed new Regulations4. These proposals also establish national contribution levels, thus removing remaining uncertainties as to the required funding.

The outlook for 2020 promises further major developments:

Bulgaria

Øthe construction of the national disposal facility has to move on steadily;

Øthe plasma melting facility has to enter into full industrial operation and create relevant know‑how; and

Øprogress will have to be made on the management of legacy waste, and decontamination and dismantling activities in the reactor building;

Slovakia

Østeady progress is expected in dismantling large components from the reactor building, including the reactor vessels, leading to the last stage of decommissioning;

Lithuania

Øthe transfer of spent‑fuel casks to the storage facility will continue seamlessly;

Øthe very low-level waste disposal facility will be used for the first time;

Øconstruction of the low-level waste disposal facility will start; and

Øpreparations for dismantling the irradiated graphite core will move to concrete action with expert support.

For the three programmes, the Commission will carry out a study on the EVM systems already in place in order to identify best practices and possible routes for ongoing improvement.

(1) Council Regulation (Euratom) No 1368/2013 of 13 December 2013 on Union support for the nuclear decommissioning assistance programmes in Bulgaria and Slovakia, and repealing Regulations (Euratom) No 549/2007 and (Euratom) No 647/2010 (OJ L 346, 20.12.2013, p. 1; correction in OJ L 8, 11.1.2014, p. 31);    
Council Regulation (Euratom) No 1369/2013 of 13 December 2013 on Union support for the nuclear decommissioning assistance programme in Lithuania, and repealing Regulation (EC) No 1990/2006 (OJ L 346, 20.12.2013, p. 7; corrections in OJ L 8, 11.1.2014, p. 30 and OJ L 121, 24.4.2014, p. 59).
(2) COM(2018) 468.
(3) Council Directive 2011/70/Euratom of 19 July 2011 establishing a Community framework for the responsible and safe management of spent fuel and radioactive waste (OJ L199, 2.8.2011, p. 48).
(4) COM(2018) 466 and COM(2018) 467.
(5) ISO 21508:2018 Earned value management in project and programme management.
(6) Вводо-водяной энергетический реактор / vodo-vodyanoi energetichesky reaktor (VVER – water‑water power reactor) is a series of pressurised water reactors.
(7) Реактор Большой Мощности Канальный / reaktor bolshoy moshchnosti kanalnyy (RBMK — high‑power channel-type reactor) is a class of graphite-moderated nuclear power reactor (also installed in Chernobyl).
(8) Optioneering is an iterative process between options identification, assessment and definition.